Bainbridge High School | Bainbridge Island, WA

Project Details
- Education
- |
- Energy
- |
- Temperature Control
- ATS Automation

Boiler Retrofit
The boilers, installed in 1998, for BHS had been oversized in the anticipation of a plant expansion that never occurred. The size coupled with the aging boiler control board had led to a degradation of the HVAC system, causing poor functionality and operation of the plant. The system pumps, and other equipment, were running 24/7 and the night setback had stopped following a schedule. To control the boilers, the District staff had manually overridden them to operate in low fire mode in order to stop them from short cycling. To address what they felt was wasteful equipment operation, Mejia and his team developed a project plan around modernizing the boiler control to save on propane and electrical use. To improve energy usage at the school, the District teamed up with ATS Automation to replace the original boiler controller, as well as program and tune the system with energy savings in mind. The original Siemens boiler PLC was replaced with Alerton’s VLC-1688 programmable controller. Boiler control was then integrated into the existing Alerton system for District staff to be able to schedule and troubleshoot from their centralized BAS. Additionally, a new operating sequence for the 3-way valves was developed, night setbacks were initiated and an aggressive scheduling plan was implemented. Now the pumps run on a schedule instead of operating 24/7, as they had been before the project was complete. The District also limited the number of individuals that could schedule the system. Now there are only two individuals in charge of scheduling the schools which has reduced the chance of the buildings running while unoccupied.
Savings
This boiler control project was completed over the summer of 2014. When comparing the high school’s utility cost from 2014 to that of 2015 there was a 36% decrease in spend. This decrease was equivalent to $267,540 in utility savings that was put back into the District’s general fund. In addition to reduced spending, equipment runtime decreased by 42% when comparing the winter months of 2014 to 2015. By having ATS install and integrate the new boiler control into the existing Alerton building automation system, the District re-established control over their boiler plant while leveraging the existing control system and extensive control knowledge of ATS engineers. 






